Merton Industrial Estate,

Merton

Client: Aviva Investors

Contract Administrator: Threelance Consulting

Value: £160,000

Programme: 7 Weeks

Zelltec Construction was contracted to deliver specialist works at Merton Industrial Estate, including the demolition of the old caretaker’s flat and adjacent unit. Services were safely isolated before demolition commenced. The site was then reduced to the required levels, with a new sub-base and tarmac laid to create an upgraded parking area. Works also included the replacement of the perimeter fencing and installation of new entrance gates, improving both security and site functionality.

  • Demolition of the old caretaker’s flat and adjacent unit

  • Isolation of all associated services prior to demolition

  • Reduction of site levels and installation of new sub-base

  • Laying of new tarmac to form an upgraded parking area

  • Replacement of perimeter fencing and installation of new entrance gates