top of page
Hedge End Trade Park Southampton 1.jpg

Hedge End Trade Park,

Southampton

Client: Maizelands Limited & Arringford Limited (Depository of Scottish Widows Property Authorised Contractual Scheme)

Contract Administrator: Jones Lang LaSalle

Value: £590,000

Programme: 12 weeks

Zelltec Construction was contracted to carry out the replacement of an attenuation tank, including all associated groundworks, at a fully operational retail park. To minimise disruption, a comprehensive site set-up was implemented, incorporating a new traffic management system with revised vehicle and pedestrian routes. These routes were carefully adjusted throughout the project to maintain safe and continuous access, ensuring the retail park remained fully operational for the duration of the works.

  • Removal and replacement of existing attenuation tank

  • Full associated groundworks

  • Installation of a temporary traffic management system

  • Creation of alternative pedestrian and vehicle access routes

  • Ongoing adjustments to maintain safe public access throughout