4 Dialog Way,
Crawley
Client: Armitage Industrial 3 Limited
Contract Administrator: Jones Lang LaSalle
Value: £1,250,000
Programme: 26 weeks
Zelltec Construction were contracted to deliver the full refurbishment of an existing industrial unit. The scope of works included extensive external upgrades to the roof, services, and access points, as well as a full internal reconfiguration and refurbishment to enhance facilities and layout. Zelltec also delivered a bespoke bathroom design to the ancillary area.
-
Demolition and removal of existing offices
-
Alteration and refurbishment of existing toilets
-
Roof repairs and coatings
-
Cladding repairs.
-
Warehouse floor repairs and coating.
-
Internal decorations.
-
External decorations.
-
Roller shutter door replacement.
-
Replacement of lighting to LED
-
Installation of AC